On completion of the construction of any part of a permanent work in the river, the Company shall as soon as practicable remove—
(a) any temporary tidal work carried out only for the purposes of part of the permanent work; and
(b) any materials, plant and equipment used for such construction,
and shall make good the site to the reasonable satisfaction of Forth Ports.

---