# The Scheme for Construction Contracts (England and Wales) Regulations 1998, Paragraph 4: Dates for payment


Any payment of a kind mentioned in paragraph 2 above shall become due on whichever of the following dates occurs later—
(a) the expiry of 7 days following the relevant period mentioned in paragraph 2(1) above, or
(b) the making of a claim by the payee.

---