In Article 4—

(a)

in paragraph 1(ee), omit “(or EUR 150 million per project in a maritime port included in the work plan of a Core Network Corridor as referred to in Article 47 of Regulation (EU) No 1315/2013 of the European Parliament and of the Council)”;

(b)

in paragraph 1(ff), omit “(or EUR 50 million per project in an inland port included in the work plan of a Core Network Corridor as referred to in Article 47 of Regulation (EU) No 1315/2013)”.