# The Storage of Carbon Dioxide (Access to Infrastructure) Regulations 2011, Regulation 19: Construction authorisations and pipeline variation notices


(1) For the purposes of sections 1 and 4 of the Pipe-lines Act 1962, the works for the construction of a relevant pipeline are deemed to have been executed in contravention of section 1(1) of that Act where the relevant pipeline is constructed—
(a) pursuant to a construction authorisation to which a variation condition is attached by virtue of regulation 7; and
(b) without conformity to that condition.
(2) For the purposes of Part 7 of the Town and Country Planning Act 1990 and Part 6 of the Town and Country Planning (Scotland) Act 1997, the construction of a relevant pipeline is deemed to have constituted a failure to comply with a condition or limitation subject to which planning permission has been granted where—
(a) a pipeline variation notice is served under regulation 8(2) in respect of the relevant pipeline; and
(b) the relevant pipeline is constructed without conformity to that notice.

---
Source: https://www.legislation.gov.uk/ukdsi/2011/9780111512777/regulation/19 (the official version)
Page: https://openlegislation.uk/draft-storage-of-carbon-dioxide-access-to-infrastructure-regulations-2011/regulation-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.