Regulation 4 Amendments in relation to fees for pre-application advice given by a Mayoral development corporation or an urban development corporation
After regulation 2A of the 2012 Regulations, insert—
“Pre-application advice given by a Mayoral development corporation or an urban development corporation
2B.(1)Subject to paragraph (2), a Mayoral development corporation or an urban development corporation, (“the corporation”), in the exercise of its planning functions within its area, may charge a fee for giving advice about applying for any permission, approval or consent under Part 3 of the 1990 Act (“pre-application advice”).
(2)The corporation may only charge a fee for pre-application advice under paragraph (1) if—
(a)it has published a copy of any proposed fee schedule—
(i)in as many newspapers as will secure that the press coverage (taken as a whole) extends to the whole of the corporation’s area; and
(ii)on its website,
at least 21 days before the fee schedule is adopted;
(b)it has adopted a fee schedule which satisfies the requirements of paragraph (3);
(c)the fee schedule has effect; and
(d)that fee is calculated in accordance with the fee schedule.
(3)The fee schedule referred to in paragraph (2) must—
(a)set out how a fee payable under paragraph (1) is to be calculated; and
(b)specify the date on which the fee schedule is to take effect.
(4)Within 5 days of adopting a fee schedule, the corporation must publish a copy of the schedule on its website and make hard copies of it available on request.”