Regulation 16 Time limits on Permit Authority

Original text. Later amendments are not shown.

(1)

A permit scheme shall set time limits within which the Permit Authority shall respond to applications for permits, provisional advance authorisations, variations of permits and variations to permit conditions.

(2)

Different time limits may be set for different cases.

(3)

If a Permit Authority does not grant or refuse a duly completed application within the applicable time limit, the application shall be deemed to have been granted and any estimate of the likely duration of the works the subject of the application for a permit or variation of a permit provided in that application shall be taken to be a reasonable period for the purposes of section 74(1) of the 1991 Act (charge for occupation of the highway where works unreasonably prolonged).