Regulation 11 Amendment of the Warm Home Discount Regulations 2011

Original text. Later amendments are not shown.

In regulation 15—

(a)

in paragraph (3)(a) after “Chapter 2” insert “and in scheme year 5 must, where reasonably practicable, be no less than the amount notified to the supplier under regulation 12(5)(b)”,

(b)

after paragraph (3) insert—

“(3A)

In scheme year 5—

(a)

a compulsory scheme electricity supplier must notify the Authority by 15th December 2015 if it considers that it will not incur at least the spending notified to it under regulation 12(5)(b);

(b)

the Authority must, within 28 days of receiving such a notification—

(i)

determine whether, and if so the extent to which, the supplier may incur spending below that amount;

(ii)

where the Authority determines that the supplier may incur spending below that amount, determine the amount by which the supplier must increase its spending under Chapter 4; and

(iii)

notify the supplier accordingly; and

(c)

a supplier must comply with a determination notified to it under sub-paragraph (b)(iii).”,

(c)

for paragraph (4)(b) substitute—

“(b)

under Chapter 4—

(i)

in scheme years 1 to 4, is the relevant percentage of £30 million; and

(ii)

in scheme year 5, is the relevant percentage of £30 million, unless the Authority has notified the supplier under paragraph (3A)(b)(iii) that spending in excess of that amount is necessary to meet the supplier’s non-core spending obligation; and”,

(d)

after paragraph (4) insert—

“(4A)

In scheme year 5, the amount of spending that a compulsory scheme electricity supplier must aim to make under Chapter 2 is the relevant percentage of the amount calculated by subtracting £30 million from the aggregate non-core spending obligation.”,

(e)

in paragraph (5) for “paragraph (4)” substitute “paragraphs (4) and (4A)”.