Regulation 17 Adjustment of non-core spending obligation: scheme year 12
The adjustments that must be made to the non-core spending obligation for scheme year 12 (“O”) of a compulsory scheme electricity supplier (“C”) are as follows.
O must be adjusted in accordance with paragraph (3) or (4) if I is less than or exceeds S where—
“I” is the amount of spending incurred by C under Part 4 of the 2011 Regulations in scheme year 11 (as determined by the Authority in accordance with regulation 29(1)(d) of those Regulations);
“S” is C’s non-core spending obligation under that Part of those Regulations for scheme year 11, as adjusted (where required) in accordance with regulation 14 of those Regulations.
If I is less than S, O must be adjusted by adding an amount equal to 9.4% of (S - I).
If I exceeds S, O must be adjusted by subtracting the lesser of—
an amount equal to 9.4% of (I - S); and
an amount equal to 9.4% of the overspend amount.
For the purposes of paragraph (4) “the overspend amount” is—
5% of S; or
where C notified the Authority of their intention to meet all or part of a failed supplier’s non-core spending obligation in accordance with regulation 30A of the 2011 Regulations in scheme year 11, 10% of S.
Whether or not an adjustment is made under paragraph (2), O must be adjusted by adding an amount equal to 9.4% of the undelivered rebate amount.
For the purposes of paragraph (6) “the undelivered rebate amount” is £140 multiplied by—
where C has made a notification under regulation 9(7) of the 2011 Regulations in respect of scheme year 11, the number of prescribed rebates as stated in that notification; and
where C has made a notification under regulation 14(3A) of the 2011 Regulations in respect of scheme year 11, the number of prescribed rebates as stated in that notification.