# Drainage (Northern Ireland) Order 1973, Paragraph 7


After the expiration of twenty-eight days from the service of notices in pursuance of paragraph 6, the Ministry may, after considering any observations sent to it under that paragraph and after holding such inquiry (if any) as the Ministry considers necessary, by order confirm the scheme in whole or in part, and either without modifications or with such modifications (which may include variations, additions or exceptions) as the Ministry considers fit (and such scheme or part thereof as so confirmed is in this Schedule referred to as a “confirmed scheme”).

---
Source: https://www.legislation.gov.uk/nisi/1973/69/schedule/7/paragraph/7 (the official version)