# The Drax Power (Generating Stations) Order 2019, Paragraph

Extent: E+W

Work No. 1 – an electricity generating station (Unit X) fuelled by natural gas and with a gross electrical output capacity of up to 1,800 megawatts including—
(a) Work No. 1A – a gas generating unit comprising—
(i) up to two gas turbines able to operate in both combined cycle and open cycle modes;
(ii) one turbine hall building for the gas turbines within this Work;
(iii) up to two heat recovery steam generators;
(iv) up to two heat recovery steam generator buildings and up to two exhaust gas emission flue stacks for the heat recovery steam generators within this Work;
(v) up to two bypass stacks;
(vi) transformers;
(vii) gas turbine air inlet filter house;
(viii) power control centre;
(ix) feed water pump house building;
(x) water supply and pipelines;
(xi) water storage tanks and pipelines;
(xii) emergency diesel generator and diesel fuel tank for safe shut-down of the plant;
(xiii) switch gear and ancillary equipment;
(xiv) up to two turbine outage store buildings;
(xv) 400 kilovolt electrical underground cables and telemetry and electrical protection auxiliary cabling connecting to Work No. 4A; and
(xvi) a new main fuel gas station comprising up to two individual fuel gas stations comprising for each—
(aa) a gas receiving area;
(bb) gas treatment and control facilities including filters, preheating and liquid collection tanks; and
(cc) other auxiliary control cabinets.
(b) Work No. 1B
(i) a new main pipe rack carrying main steam and condensate, and auxiliary cabling and pipework between the heat recovery steam generators and the existing steam turbine;
(ii) piling for foundations to accommodate the pipe rack including in connection with the pipe rack comprising part of Work No. 2B; and
(iii) modifications to the existing steam turbine, generating plant and turbine hall building.
(c) Work No. 1C – a new underground gas pipeline across New Road connecting Work No. 1A to Work No. 5.
(d) Work No. 1D – in connection with and in addition to Work Nos. 1A, 1B and 1C—
(i) works connecting Work Nos. 1A, 1B and 1C to existing equipment and utilities;
(ii) ground raising and ground preparation works;
(iii) site lighting infrastructure, including perimeter lighting columns;
(iv) internal roadways, car parking, pedestrian network, cycle parking and hardstanding;
(v) site drainage and waste management infrastructure, including relocation of existing infrastructure as required;
(vi) electricity (including a 132 kilovolt electricity cable across New Road connecting Work No. 1A to Work No.5), water, wastewater and telecommunications and other services; and
(vii) hard and soft landscaping including tree planting, ecological mitigation, temporary and permanent fencing and other boundary treatments.

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/1/paragraph/wrapper3n1 (the official version)