# The Drax Power (Generating Stations) Order 2019, Paragraph

Extent: E+W

Work No. 3 – up to two battery storage facilities including—
(a) Work No. 3A – one battery storage facility (in connection with Unit X) comprising—
(i) battery energy storage cells with converters;
(ii) a structure protecting the battery energy storage cells;
(iii) transformers;
(iv) switch gear and ancillary equipment;
(v) electrical underground cable connecting to Work No. 1A;
(vi) ground raising and ground preparation works;
(vii) a flood mitigation channel;
(viii) site lighting infrastructure, including lighting columns; and
(ix) hard and soft landscaping including tree planting, ecological mitigation, temporary and permanent fencing and other boundary treatments.
(b) Work No. 3B – one battery storage facility (in connection with Unit Y) comprising—
(i) battery energy storage cells with converters;
(ii) a structure protecting the battery energy storage cells or infrastructure to include the battery energy storage cells in the structures within Work No.3A(ii);
(iii) transformers;
(iv) switch gear and ancillary equipment; and
(v) electrical underground cable connecting to Work No. 2A.

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/1/paragraph/wrapper5n1 (the official version)
Page: https://openlegislation.uk/drax-power-generating-stations-order-2019/schedule-1/paragraph-wrapper5n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.