# The Drax Power (Generating Stations) Order 2019, Part 2: UNIT X PARAMETERS

Extent: E+W

Table 13
Component
Work No.
Maximum length (m)
Maximum width (m)
Maximum height (m AGL)
Maximum height (m AOD)
Turbine hall building
1A(ii)
87
23
28
34
Heat recovery steam generator building (up to two)
1A(iv)
55
29
49
55
Exhaust gas emission flue stacks (up to two)
1A(iv)
–
–
123
129
Bypass stack (up to two) (excluding supporting structures)
1A(v)
–
–
123
129
Transformers
1A(vi)
36
20
11
17
Gas turbine air inlet filter house
1A(vii)
26
27
35
41
Power control centre
1A(viii)
17
17
6
12
Turbine outage store building (up to two)
1A(xiv)
113
43
28
34
Fuel gas station (up to two)
1A(xvi)
26
19
7
13
Main pipe rack
1B(i)
600
12
25
31
Battery storage facility including any structure (where constructed in its entirety in a single stage being stage 1)
3A
180
60
10
16
Battery storage facility including any structure (where constructed in two stages being stage 1 and stage 2)
3A
90
60
10
16
Gas insulated switchgear banking building
4A
18
12
11
17
Control room building for gas insulated switchgear
4A
26
12
11
17
Gas receiving facility (GRF) Compound
5
85
85
10
16
Pig Trap Facility (Launching) Compound
6B
30
30
5
10
Minimum Offtake Connection
6A
30
30
5
10
Reinstatement of sludge lagoon
12A
82
55
–
–
Table 14
Component
Work No.
Minimum height (m AGL)
Minimum height (m AOD)
Exhaust gas emission flue stacks (up to two)
1A(iv)
122.5
128.5
Bypass Stack (up to two) (excluding supporting structures)
1A(v)
122.5
128.5

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/13/part/2 (the official version)