  "heading": "DOCUMENTS AND PLANS TO BE CERTIFIED",
  "text": "Table 17\n(1)Document name\n(2)Document reference\n(3)Revision number\n(4)Date\nthe access and rights of way plans\nKey plan: 2.4\n01\n21.05.2018\nSheet 2: 2.4\n02\n07.11.2018\nSheet 3: 2.4\n01\n21.05.2018\nSheet 4: 2.4\n01\n21.05.2018\nSheet 5: 2.4\n02\n06.12.2018\nSheet 6: 2.4\n01\n21.05.2018\nSheet 7: 2.4\n01\n21.05.2018\nSheet 8: 2.4\n01\n21.05.2018\nSheet 9: 2.4\n01\n21.05.2018\nSheet 10: 2.4\n01\n21.05.2018\nSheet 11: 2.4\n01\n21.05.2018\nSheet 12: 2.4\n01\n21.05.2018\nSheet 13: 2.4\n01\n21.05.2018\nSheet 14: 2.4\n01\n21.05.2018\nSheet 15: 2.4\n01\n21.05.2018\nSheet 16: 2.4\n01\n21.05.2018\nSheet 17: 2.4\n01\n21.05.2018\nSheet 18: 2.4\n01\n21.05.2018\nSheet 19: 2.4\n01\n21.05.2018\nSheet 20: 2.4\n01\n21.05.2018\nSheet 21: 2.4\n01\n21.05.2018\nSheet 22: 2.4\n01\n21.05.2018\nSheet 23: 2.4\n01\n21.05.2018\nthe application guide\n1.2\n014\n03.04.2019\nthe book of reference\n4.3A\n007\n21.03.2019\nthe CHP statement\n5.6\n002\n22.11.2018\nthe environmental statement\nenvironmental statement volume 1: 6.1 (excluding chapter 3)\n001 (excluding chapter 3)\n29.05.2018 (excluding chapter 3)\nenvironmental statement volume 1: 6.1 (chapter 3)\n002\n30.01.2019\nenvironmental statement volume 2: 6.2\nappendices 1.1, 1.2, 3.1, 5.3, 5.4, 5.5, 5.6, 5.7, 5.8, 6.1, 6.2, 6.3, 7.1, 7.2, 7.3, 8.1, 8.2, 8.3, 9.1, 9.2, 9.3, 9.4, 9.5, 9.6, 9.7, 9.8, 9.9, 10.1, 10.2, 10.3, 10.4, 10.5, 11.1, 15.1, 16.1, 16.2, 16.3, 16.4, 17.1, 17.2, 17.3\n001\n29.05.2018 (submission date)\nappendix 9.10\n003\n28.03.2019\nappendices 5.1 and 5.2\n003\n13.12.2018\nenvironmental statement volume 3: 6.3\n001\n22.05.2018\nbreeding bird survey: 8.4.2\n001\nSeptember 2018\nreptile survey: 8.4.3\n001\n20.09.2018\nbat activity survey: 8.4.4\n001\nOctober 2018\ncover letter in relation to removal of stage 0, the site reconfiguration works, from the application\nN/A\n08.11.2018\nremoval of stage 0 mitigation review: 8.5.5\n001\n07.11.2018\nassessment of non-material amendments to proposed scheme: 8.4.8\n001\n14.11.2018\nerrata – environmental statement (chapters 7, 8 and 11): 8.3.1\n001\n03.10.2018\nupdate to the cumulative assessment: 8.4.9\n001\n15.11.2018\nthe flood risk assessment\n6.8\n003\n08.11.2018\nthe land plans\nKey plan: 2.2\n03\n06.11.2018\nSheet 2: 2.2\n04\n04.01.2019\nSheet 3: 2.2\n03\n06.11.2018\nSheet 4: 2.2\n03\n06.11.2018\nSheet 5: 2.2\n04\n04.01.2019\nSheet 6: 2.2\n03\n06.11.2018\nSheet 7: 2.2\n02\n07.11.2018\nSheet 8: 2.2\n03\n06.11.2018\nSheet 9: 2.2\n02\n07.11.2018\nthe outline construction environmental management plan\n6.5\n005\n18.03.2018\nthe outline construction traffic management plan\n6.2.5.2\n003\n13.12.2018\nthe outline construction worker travel plan\n6.2.5.1\n003\n13.12.2018\nthe outline public right of way management plan\n8.4.6\n003\n20.02.2019\nthe outline landscape and biodiversity strategy\n6.7\n005\n28.03.2019\nthe works plans\nKey plan: 2.3A\n04\n13.12.2018\nSheet 2: 2.3A\n02\n22.10.2018\nSheet 3: 2.3A\n01\n16.05.2018\nSheet 4: 2.3A\n01\n16.05.2018\nSheet 5: 2.3A\n02\n22.10.2018\nSheet 6: 2.3A\n02\n22.10.2018\nSheet 7: 2.3A\n02\n22.10.2018\nSheet 8: 2.3A\n01\n16.05.2018\nSheet 9: 2.3A\n01\n16.05.2018\nSheet 10: 2.3A\n02\n22.10.2018\nSheet 11: 2.3A\n02\n22.10.2018\nSheet 12: 2.3A\n01\n16.05.2018\nSheet 13: 2.3A\n01\n16.05.2018\nSheet 14: 2.3A\n01\n16.05.2018\nSheet 15: 2.3A\n01\n16.05.2018\nSheet 16: 2.3A\n01\n16.05.2018\nSheet 17: 2.3A\n01\n16.05.2018\nSheet 18: 2.3A\n01\n16.05.2018\nSheet 19: 2.3A\n02\n22.10.2018\nSheet 20: 2.3A\n01\n16.05.2018\nSheet 21: 2.3A\n02\n22.10.2018\nSheet 22: 2.3A\n01\n16.05.2018\nSheet 23: 2.3A\n01\n16.05.2018\nSheet 24: 2.3A\n03\n22.10.2018\nSheet 25: 2.3A\n02\n22.10.2018\nSheet 26: 2.3A\n02\n29.06.2018\nSheet 27: 2.3A\n01\n16.05.2018\nSheet 28: 2.3A\n01\n16.05.2018\nSheet 29: 2.3A\n01\n16.05.2018\nSheet 30: 2.3A\n02\n22.10.2018\nSheet 31: 2.3A\n02\n22.10.2018\nSheet 32: 2.3A\n02\n22.10.2018\nSheet 33: 2.3A\n01\n16.05.2018\nSheet 34: 2.3A\n01\n16.05.2018\nSheet 35: 2.3A\n01\n09.05.2018\nSheet 36: 2.3A\n01\n16.05.2018\nSheet 37: 2.3A\n02\n22.10.2018\nSheet 38: 2.3A\n01\n16.05.2018\nSheet 39: 2.3A\n01\n16.05.2018\nSheet 40: 2.3A\n01\n16.05.2018\nSheet 41: 2.3A\n01\n16.05.2018\nSheet 42: 2.3A\n01\n16.05.2018",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Words in Sch. 14 Table 17 substituted (19.8.2020) by The Drax Power (Generating Stations) (Correction) Order 2020 (S.I. 2020/879), art. 1(2), Sch."
    },
    {
      "type": "F",
      "label": "F2",
      "text": "Words in Sch. 14 Table 17 inserted (19.8.2020) by The Drax Power (Generating Stations) (Correction) Order 2020 (S.I. 2020/879), art. 1(2), Sch."
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 14 in force at 25.10.2019, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2019/1315/schedule/14",
    "retrieved_at": "2026-10-28T22:36:58.505253+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}