# The Drax Power (Generating Stations) Order 2019, Paragraph 10: External lighting during construction and operation

Extent: E+W

(1) No part of the numbered works comprising stage 1 may commence until a written scheme for the temporary external lighting to be installed for the purposes of construction for that work has been submitted to and approved by the relevant planning authority.
(2) No part of the numbered works comprising stage 2 may commence until a written scheme for the temporary external lighting to be installed for the purposes of construction for that numbered work has been submitted to and approved by the relevant planning authority.
(3) The schemes submitted and approved pursuant to sub-paragraphs (1) and (2) of this Requirement must be substantially in accordance with the principles set out in chapter 9 (biodiversity) and chapter 10 (landscape and visual amenity) of the environmental statement and the objectives set out in the outline construction environmental management plan and must include details of the temporary external lighting to be installed for the purposes of the construction of the relevant numbered work.
(4) Prior to the date of Work No. 1A full commissioning a written scheme for the permanent external lighting to be installed for the purposes of operation for the numbered works comprising stage 1 must be submitted to and approved by the relevant planning authority.
(5) Prior to the date of Work No. 2A full commissioning a written scheme for the permanent external lighting to be installed for the purposes of operation for the numbered works comprising stage 2 must be submitted to and approved by the relevant planning authority.
(6) The schemes submitted and approved pursuant to sub-paragraphs (4) and (5) of this Requirement must be substantially in accordance with the principles set out in chapter 9 (biodiversity) and chapter 10 (landscape and visual amenity) of the environmental statement and must include details of the permanent external lighting to be installed for the purposes of the operation of the relevant numbered work.
(7) The schemes must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/2/paragraph/10 (the official version)
Page: https://openlegislation.uk/drax-power-generating-stations-order-2019/schedule-2/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.