# The Drax Power (Generating Stations) Order 2019, Paragraph 18: Construction traffic management plan

Extent: E+W

(1) No part of the authorised development may commence, except for numbered works 11, 13 and 14, until a construction traffic management plan has, for that part, been submitted to and, after consultation with Highways England and the highway authority, approved by the relevant planning authority.
(2) The plan submitted and approved pursuant to sub-paragraph (1) must be substantially in accordance with the relevant part of the outline construction traffic management plan.
(3) Notices must be erected and maintained by the undertaker throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site.
(4) The plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/drax-power-generating-stations-order-2019/schedule-2/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.