# The Drax Power (Generating Stations) Order 2019, Paragraph 24: Air safety

Extent: E+W

No part of the authorised development may commence until the undertaker has submitted confirmation to the relevant planning authority that it has provided details of the information that is required by the Defence Geographic Centre of the Ministry of Defence to chart the site for aviation purposes.

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/2/paragraph/24 (the official version)
Page: https://openlegislation.uk/drax-power-generating-stations-order-2019/schedule-2/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.