# The Drax Power (Generating Stations) Order 2019, Paragraph 25: Local liaison committee

Extent: E+W

(1) The authorised development must not commence until the undertaker has established a committee to liaise with local residents and organisations about matters relating to the authorised development (a “local liaison committee”).
(2) The undertaker must invite the relevant planning authority and other relevant interest groups, as may be agreed with the relevant planning authority, to nominate representatives to join the local liaison committee.
(3) The undertaker must provide a full secretariat service and supply an appropriate venue for the local liaison committee meetings to take place.
(4) The local liaison committee must—
(a) include representatives of the undertaker;
(b) meet every other month, starting in the month prior to commencement of stage 1 until the date of Work No. 1A full commissioning, or if stage 2 has commenced prior to the date of Work No. 1A full commissioning, the date of Work No. 2A full commissioning, unless otherwise agreed by the majority of the members of the local liaison committee;
(c) if stage 2 has not commenced prior to the date of Work No. 1A full commissioning, meet every month, starting in the month prior to commencement of stage 2 until the date of Work No. 2A full commissioning, unless otherwise agreed by the majority of the members of the local liaison committee; and
(d) during the operation of the authorised development meet once a year unless otherwise agreed by the majority of the members of the local liaison committee.

---
Source: https://www.legislation.gov.uk/uksi/2019/1315/schedule/2/paragraph/25 (the official version)
Page: https://openlegislation.uk/drax-power-generating-stations-order-2019/schedule-2/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.