# The Drax Power (Generating Stations) Order 2019, Part 1: PERMANENT ALTERATION OF LAYOUT

Extent: E+W

Table 2
(1) Area
(2) Streets subject to alteration of layout
(3) Description of alteration
In the District of Selby
New Road
Works for the provision of a new permanent access to Work No. 5 on the east side of New Road between the points marked AI and AJ on sheet 3 of the access and rights of way plans
In the District of Selby
Rusholme Lane
Works for the provision of a new permanent access to Work No. 6 on the south side of Rusholme Lane between the points marked AW and AV on sheet 8 of the access rights of way plans

---