# The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024, Paragraph 33: Arbitration


Save for differences or disputes arising under paragraphs 25(2), 25(4), 26(1) and 27 any difference or dispute arising between the undertaker and National Grid under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid, be determined by arbitration in accordance with article 40 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2024/70/schedule/12/paragraph/33 (the official version)
Page: https://openlegislation.uk/drax-power-station-bioenergy-with-carbon-capture-and-storage-extension-order-2024/schedule-12/paragraph-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.