# The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024, Paragraph 10: Surface water drainage


(1) Each of numbered works 1, 2 and 3 of the authorised development must not commence until a surface water drainage scheme for that numbered work has been submitted to, and after consultation with the Environment Agency, lead local flood authority and relevant internal drainage board, approved by the relevant planning authority.
(2) The surface water drainage scheme submitted and approved pursuant to sub-paragraph (1) must be substantially in accordance with the principles set out in sections 5 and 6 of the proposed surface water drainage strategy.
(3) The schemes must be implemented and maintained as approved throughout the operation of the numbered works to which they relate.

---
Source: https://www.legislation.gov.uk/uksi/2024/70/schedule/2/paragraph/10 (the official version)
Page: https://openlegislation.uk/drax-power-station-bioenergy-with-carbon-capture-and-storage-extension-order-2024/schedule-2/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.