# The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024, Paragraph 3: Notice of date of full commissioning


(1) Within seven days of the completion of the commissioning of numbered works 1(D)(i), (iii) and (v), the undertaker must provide the relevant planning authority with notice of the date of Unit 1 full commissioning.
(2) Within seven days of the completion of the commissioning of numbered works 1(D)(ii), (iv) and (vi), the undertaker must provide the relevant planning authority with notice of the date of Unit 2 full commissioning.

---