# The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024, Paragraph 4: Requirement for written approval


Where under any of these requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.

---