# The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024, Part 2: LAND IN WHICH RIGHTS MAY BE EXTINGUISHED


(1)
Number of plot shown on the land plans
(2)
Rights etc. which may be extinguished
01-17
Extinguishment of existing rights in order to facilitate construction and operation of Work Nos. 2, 3, 4, 5 and 6
01-18
Extinguishment of existing rights in order to facilitate construction and operation of Work Nos. 2, 3, 4 and 5
01-19
Extinguishment of existing rights in order to facilitate construction and operation of Work Nos. 1, 2, 3, 4, 5 and 6
01-24
Extinguishment of existing rights in order to facilitate construction and operation of Work Nos. 1F, 3, 4 and 5
01-78, 01-80, 01-90
Extinguishment of existing rights relating to existing telecommunications apparatus

---
Source: https://www.legislation.gov.uk/uksi/2024/70/schedule/8/part/2 (the official version)
Page: https://openlegislation.uk/drax-power-station-bioenergy-with-carbon-capture-and-storage-extension-order-2024/schedule-8/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.