# The East Anglia ONE Offshore Wind Farm Order 2014, Article 3: Development consent etc. granted by the Order

Extent: E+W+S

(1) Subject to the provisions of this Order and to the Requirements the undertakers is granted—
(a) development consent for the authorised development; and
(b) consent for the ancillary works,
to be carried out within the Order limits.
(2) Subject to the Requirements, Works No. 1 to 3A shall be constructed anywhere within the Order limits seaward of mean high water springs and Works No. 3B to 41 shall be constructed anywhere within the Order limits landward of mean low water.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/article/3 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/article-3