# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 10: Detailed design approval onshore

Extent: E+W+S

(1) No part of Work No. 39 shall commence until details of the layout, scale and external appearance of the same, have been submitted to and approved in writing by the relevant planning authority. Work No. 39 must be carried out in accordance with the approved details.
(2) Any details provided by the undertakers pursuant to sub-paragraph (1) must accord with the outline converter station design principles statement and be within the Order limits.
(3) No building comprised in Work No. 39 shall exceed 79 metres AOD for the HVDC option and 75 metres AOD for the HVAC option and no external electrical equipment comprised in Work No. 39 shall exceed 64 metres AOD for the HVDC option and 69 metres AOD for the HVAC option.
(4) The total footprint of the buildings housing the converters comprised in Work No. 39 must not exceed 130 metres in length and 85 metres in width for the HVDC option and for the HVAC option.
(5) The fenced compound (excluding its accesses) comprised in Work No. 39 must not exceed 190 metres by 150 metres.
(6) The working width of the onshore cable corridor must not exceed 55 metres, save in respect of the following—
(a) works for which horizontal directional drilling is proposed for the purpose of passing under the relevant obstruction named in the relevant Work No., as follows—
(i) Work No. 3B for which the working width of the onshore cable corridor must not exceed 160 metres;
(ii) Work No. 7A for which the working width of the onshore cable corridor must not exceed 160 metres;
(iii) Work No. 14 for which the working width of the onshore cable corridor must not exceed 110 metres;
(iv) Work No. 19 for which the working width of the onshore cable corridor must not exceed 160 metres;
(v) Work No. 24 for which the working width of the onshore cable corridor must not exceed 120 metres;
(vi) Work No. 26 for which the working width of the onshore cable corridor must not exceed 120 metres;
(vii) Work No. 33A for which the working width of the onshore cable corridor must not exceed 160 metres;
(viii) Work No. 35A for which the working width of the onshore cable corridor must not exceed 130 metres;
(ix) Work No. 37A for which the working width of the onshore cable corridor must not exceed 130 metres;
(b) plot 340 in the book of reference within Work No. 31 must not exceed 97 metres.
(7) Works No. 3B, 7A, 14, 19, 24, 26, 33A, 35A, and 37A must comprise horizontal directional drilling for the purpose of passing under the relevant obstruction named in the relevant Work No.
(8) In the event of the use of open trenching for construction of the connection works at Work No. 26, that open trenching must be carried out in accordance with figure 6.1 of the further environmental information.
(9) The footprint of the construction consolidation sites must not exceed the following—
(a) 15,000 metres2 in the case of primary construction consolidation sites; or
(b) 10,000 metres2 in the case of secondary construction consolidation sites.
(10) In relation to the kiosks to be located within the onshore cable corridor—
(a) no stage of the connection works shall commence until details of the scale and appearance of the kiosks have been submitted to and approved in writing by the relevant planning authority;
(b) the footprint of each kiosk must not exceed 1 metre in width, 0.75 metres in length and 1 metres in height; and
(c) the kiosks must be constructed in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/1/paragraph/10 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-1/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.