# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 35: Transmission system

Extent: E+W+S

(1) Prior to commencement of construction of the authorised development, the undertaker must give written notice to the Secretary of State, the relevant planning authority and the MMO detailing the selection made by the undertaker under Work No. 1 to construct either the HVDC offshore wind farm, using the HVDC option, or the HVAC offshore wind farm, using the HVAC option.
(2) Where under sub-paragraph (1) the HVAC option is selected, the written notice shall also specify whether the HVAC collector stations are to be constructed under Work No. 1(b) or Work No. 2.
(3) The authorised development must be constructed using either, wholly, the HVAC option or the HVDC option and no combination of the two is permitted.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/1/paragraph/35 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-1/paragraph-35
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.