# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 5


(1) The total number of offshore substations forming part of the authorised development must not exceed five for the HVDC option or two for the HVAC option (whether constructed under Work No. 1 or Work No. 2).
(2) The dimensions of any HVAC offshore collector stations for the HVDC option forming part of the authorised development (excluding towers, helipads, masts and cranes) must not exceed 60 metres in height when measured from LAT, 30 metres in length and 40 metres in width.
(3) The dimensions of any HVDC offshore converter stations for the HVDC option forming part of the authorised development (excluding towers, helipads, masts and cranes) must not exceed 60 metres in height when measured from LAT, 75 metres in length and 120 metres in width.
(4) The dimensions of any HVAC offshore collector stations for the HVAC option forming part of the authorised development (excluding towers, helipads, masts and cranes) must not exceed 60 metres in height when measured from LAT, 75 metres in length and 120 metres in width

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/1/paragraph/5 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-1/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.