(1) The total length of the cables comprising Work No. 3A must not exceed 400 kilometres for the HVDC option and 250 kilometres for the HVAC option.
(2) The total length of the cables comprising Work No. 1(d) must not exceed 680 kilometres for the HVDC option and 350 kilometres for the HVAC option.
(3) The total amount of cable protection for the cables comprising Work No. 3A must not exceed 24,000 metres3 for the HVDC option and 15,000 metres3 for the HVAC option.
(4) The total amount of cable protection for the cables comprising Work No. 1(d) must not exceed 3,000 metres3 for the HVDC option and 3,000 metres3 for the HVAC option.

---