# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 1: Interpretation

Extent: E+W+S

In this Part of this Schedule—
“AOD” means above ordnance datum;
“highway authority” means the local highway authority for the relevant area;
“onshore cable corridor” means the onshore area in which the cables will be located within the Order limits;
“stage” means one of the nine stages of the connection works comprised in—
(i)Works No. 3B and 3C (using the construction consolidation site at Work No. 4);
(ii)Works No. 5 to 7A (using the construction consolidation site at Work No. 7B);
(iii)Works No. 8 to 10A (using the construction consolidation site at Work No. 10B);
(iv)Works No. 11 to 15(using the construction consolidation site at Work No. 16);
(v)Works No. 17 to 23A (using the construction consolidation site at Work No. 23B);
(vi)Works No. 23C to 28A (using the construction consolidation site at Work No. 28B);
(vii)Works No. 29 to 30A (using the construction consolidation site at Work No. 30B);
(viii)Works No. 31 to 34A (using the construction consolidation site at Work No. 34B);
(ix)Works No. 35A to 37D (using the construction consolidation site at Work No. 37E);
(x)Works No. 38 to 41;
or such other stage of the connection works agreed in writing with the relevant local planning authority;
“working width” means the construction width of the onshore cable corridor including haul route, spoil storage and temporary drainage during installation of cables and/or cable ducts.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/1/part/3/paragraph/1 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-1/part-3/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.