# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 13: Foundation restrictions

Extent: E+W+S

No gravity base foundations may be installed in any area of the seabed with mobile sand waves of 5 metres or more, as identified by the swath-bathymetry survey carried out under condition 17(2)(c), unless otherwise agreed in writing by the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/11/paragraph/13 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-11/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.