# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 17: Construction monitoring

Extent: E+W+S

(1) The undertakers must, in discharging condition 11(b), submit details for approval by the MMO in consultation with Natural England and JNCC of any proposed monitoring, including methodologies and timings, to be carried out during the construction of the authorised scheme. The survey proposals must specify each survey’s objectives.
(2) Construction monitoring must include traffic monitoring in accordance with the outline navigation monitoring strategy, including the provision of reports on the results of that monitoring periodically as requested by the MCA.
(3) The undertakers must carry out the surveys approved under sub-paragraph (1) and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with Natural England and JNCC.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/11/paragraph/17 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-11/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.