# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 9: Force majeure

Extent: E+W+S

If, due to stress of weather or any other cause the master of a vessel determines that it is necessary to deposit the authorised deposits outside of the Order limits because the safety of human life and/or of the vessel is threatened, within 48 hours full details of the circumstances of the deposit must be notified to the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2014/1599/schedule/11/paragraph/9 (the official version)
Page: https://openlegislation.uk/east-anglia-one-offshore-wind-farm-order-2014/schedule-11/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.