# The East Anglia ONE Offshore Wind Farm Order 2014, Paragraph 20

Extent: E+W+S

The undertakers must give written notice to Network Rail where any application is proposed to be made by the undertakers for the Secretary of State’s consent under article 5 (benefit of the Order) of this Order and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—
(a) the nature of the application to be made;
(b) the extent of the geographical area to which the application relates; and
(c) the name and address of the person acting for the Secretary of State to whom the application is to be made.

---