# The East Anglia THREE Offshore Wind Farm (Correction) Order 2018, Introduction: Introductory text


Infrastructure Planning
Made 12th July 2018
Coming into force 13th July 2018
The East Anglia THREE Offshore Wind Farm Order 2017 (“the 2017 Order”), which granted development consent within the meaning of the Planning Act 2008 (“the Act”), contains correctable errors within the meaning of the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicant for the correction of errors and omissions in the 2017 Order.
The Secretary of State has informed Suffolk Coastal District Council and Mid Suffolk District Council, as the relevant local planning authorities for the area in which the land to which the 2017 Order relates is situated, that the request has been received in accordance with paragraph 1(7) of Schedule 4 to the Act.
The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.

---
Source: https://www.legislation.gov.uk/uksi/2018/843/introduction (the official version)