# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 11: Stages and phasing of authorised development onshore

Extent: E+W+S

(1) The connection works may not be commenced until a written scheme setting out the stages of the connection works has been submitted to, and approved by, the relevant planning authority
(2) Work No. 67 may not be commenced until a written scheme setting out whether it is to be carried out in a single onshore phase or in two onshore phases has been submitted to, and approved by, the relevant planning authority.
(3) In the event that Work No. 67 is to be carried out in two onshore phases, at least 14 days’ prior notice of commencement of the second onshore phase must be given to the relevant planning authority.
(4) The written schemes specified in paragraphs (1) and (2) must be implemented as approved by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/1/paragraph/11 (the official version)
Page: https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-1/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.