# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 19: Contaminated land and groundwater

Extent: E+W+S

(1) Work No. 41 must not commence until a written scheme applicable to that work, to mitigate the potential for release of contaminants within the Order limits has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority.
(2) The written scheme referred to in paragraph (1) must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/1/paragraph/19 (the official version)
Page: https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-1/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.