{
  "url": "https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-1/paragraph-31",
  "json_url": "https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-1/paragraph-31.json",
  "legislation": "uksi/2017/826",
  "legislation_title": "The East Anglia THREE Offshore Wind Farm Order 2017",
  "legislation_url": "https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017",
  "path": "schedule/1/paragraph/31",
  "kind": "paragraph",
  "number": "31",
  "heading": "Onshore decommissioning",
  "text": "(1) Within three months of the cessation of commercial operation of the connection works an onshore decommissioning plan must be submitted to and approved by the relevant planning authority.\n(2) The decommissioning plan must be implemented as approved.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 3 para. 31 in force at 29.8.2017, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2017/826/schedule/1/paragraph/31",
    "retrieved_at": "2026-10-28T23:08:55.389095+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}