# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 31: Onshore decommissioning

Extent: E+W+S

(1) Within three months of the cessation of commercial operation of the connection works an onshore decommissioning plan must be submitted to and approved by the relevant planning authority.
(2) The decommissioning plan must be implemented as approved.

---