# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 9


(1) The undertaker must colour all structures yellow (colour code RAL 1023) from at least highest astronomical tide to a height directed by Trinity House, or must colour the structure as directed by Trinity House from time to time.
(2) Subject to sub-paragraph (1) above, unless the MMO otherwise directs, the undertaker must ensure that the wind turbine generators are painted light grey (colour code RAL 7035).

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/10/part/2/paragraph/9 (the official version)