# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 16: Foundation restrictions

Extent: E+W+S

No gravity base foundations may be installed in any area of the seabed with mobile sand waves of five metres or more, as identified by the swath-bathymetry survey carried out under condition 17(2)(b), unless otherwise agreed in writing by the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/13/paragraph/16 (the official version)
Page: https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-13/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.