Licensed activities must not take place within the restricted area until the MMO has confirmed in writing that it is satisfied with the results of a sediment sample survey or that sufficient mitigation has been secured in the approved method statement required to be submitted under condition 13(1)(g), to prevent impacts from contaminated sediment.

---