# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 5


The total length of the cables and the volume of their cable protection must not exceed the following—
Work
Length
Cable protection
Work No. 3 (platform link)
165 kilometres
19,580 m3
Work No. 5A (export cable)
332 kilometres
40,630 m3

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/13/part/2/paragraph/5 (the official version)