# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 29

Extent: E+W+S

Any additional expenses which Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, are to be repaid by the undertaker to Network Rail.

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/8/paragraph/29 (the official version)