# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 45

Extent: E+W+S

If for any reason or in consequence of the construction of any of the works referred to in paragraphs 40 to 42 and 44 above any damage is caused to any Apparatus (other than Apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker must,
(a) bear and pay the cost reasonably incurred by Anglian Water in making good any damage or restoring the supply; and
(b) make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs properly and reasonably incurred by Anglian Water
by reason or in consequence of any such damage or interruption.

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/8/paragraph/45 (the official version)
Page: https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-8/paragraph-45
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.