# The East Anglia THREE Offshore Wind Farm Order 2017, Paragraph 49: Interpretation

Extent: E+W+S

(1) In this Part of this Schedule—
“1991 Act” means the New Roads and Street Works Act 1991;
“alternative apparatus” means appropriate alternative apparatus to the satisfaction of the statutory undertaker to enable the statutory undertaker to fulfil its statutory functions in a manner no less efficient than previously;
“apparatus” means—
(a)in the case of an electricity undertaker, electric lines or electrical plant as defined in the 1989 Act, belonging to or maintained by that undertaker;
(b)in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or maintained by a gas transporter for the purposes of gas supply;
together with any replacement apparatus and such other apparatus constructed pursuant to the Order that becomes operational apparatus of the statutory undertaker for the purposes of transmission, distribution and/or supply and includes any structure in which apparatus is or must be lodged or which gives or will give access to apparatus;
“authorised works” has the same meaning as is given to the term “authorised development” in article 2 of this Order and includes any associated development authorised by the Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Schedule;
“deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary and/or replace existing easements, agreement, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
“functions” includes powers and duties;
“ground mitigation scheme” means a scheme approved by the statutory undertaker (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
“ground monitoring scheme” means a scheme for monitoring ground subsistence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, must require the undertaker to submit for the statutory undertaker’s approval a ground mitigation scheme;
“ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
“maintain” and “maintenance” includes the ability and right to do any of the following in relation to any apparatus or alternative apparatus of the statutory undertaker including construct, use, repair, alter, inspect, renew or remove the apparatus;
“plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
“parent company” means a parent company of the undertaker acceptable to and which must have been approved by the statutory undertaker acting reasonably;
“statutory undertaker” means, as appropriate—
(a)an electricity undertaker being a licence holder within the meaning of Part 1 of the 1989 Act; and
(b)a gas transporter within the meaning of Part 1 of the Gas Act 1986.
“specified works” means any of the authorised works or activities undertaken in association with the authorised works which :
(a)will or may be situated over or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under paragraph 52 (2) or otherwise;
(b)may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under paragraph 52 (2) or otherwise; and/or
(c)include any of the activities that are referred to in paragraph 8 of T/SP/SSW/22 (the statutory undertaker’s policies for safe working in proximity to gas apparatus “Specification for safe working in the vicinity of National Grid, High pressure Gas pipelines and associated installation requirements for third parties T/SP/SSW/22” );
(2) Except for paragraphs 50 (apparatus of statutory undertakers in stopped up streets), 54 (Retained apparatus protection: Gas Undertakers), 55 (Retained apparatus protection: Electricity Undertakers), 56 (expenses) and 57 (Indemnity) of this Schedule which must apply in respect of the exercise of all or any powers under this Order affecting the rights and apparatus of the undertaker, the other provisions of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and the statutory undertaker are regulated by the provisions of Part 3 of the 1991 Act.

---
Source: https://www.legislation.gov.uk/uksi/2017/826/schedule/8/paragraph/49 (the official version)
Page: https://openlegislation.uk/east-anglia-three-offshore-wind-farm-order-2017/schedule-8/paragraph-49