# The East Anglia TWO Offshore Wind Farm Order 2022, Paragraph 18: Contaminated land and groundwater

Extent: E+W+S

(1) No stage of the onshore works shall commence until a written scheme applicable to that stage, to mitigate the potential for release of contaminants within the Order limits has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority.
(2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the relevant planning authority, to identify the extent of any contamination within the Order limits comprised in that stage and mitigation measures to be undertaken to limit impacts arising from the potential release of contaminants.
(3) The written scheme referred to in sub-paragraph (1) must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2022/433/schedule/1/paragraph/18 (the official version)
Page: https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-1/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

