{
  "url": "https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-1/paragraph-19",
  "json_url": "https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-1/paragraph-19.json",
  "legislation": "uksi/2022/433",
  "legislation_title": "The East Anglia TWO Offshore Wind Farm Order 2022",
  "legislation_url": "https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022",
  "path": "schedule/1/paragraph/19",
  "kind": "paragraph",
  "number": "19",
  "heading": "Pre-commencement archaeology execution plan",
  "text": "(1) No intrusive onshore preparation works (including pre-commencement archaeological surveys, archaeological investigations or site preparation works in respect of such surveys or investigations) may be carried out until a pre-commencement archaeology execution plan (which accords with the outline pre-commencement archaeology execution plan and the outline written scheme of investigation (onshore archaeology)) in respect of those works has been submitted to and approved by Suffolk County Council in consultation with the relevant planning authority.\n(2) Intrusive onshore preparation works must be carried out in accordance with the approved plan.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 Pt. 3 para. 19 in force at 22.4.2022, see art. 1(2)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2022/433/schedule/1/paragraph/19",
    "retrieved_at": "2026-10-28T22:01:13.677247+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}