# The East Anglia TWO Offshore Wind Farm Order 2022, Paragraph 29: Restoration of land used temporarily for construction

Extent: E+W+S

Any land landward of mean low water springs within the Order limits which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated, in accordance with such details as the relevant planning authority in consultation with the relevant highway authority may approve, within twelve months of completion of the relevant stage of the onshore works or such other period as the relevant planning authority may approve.

---