# The East Anglia TWO Offshore Wind Farm Order 2022, Paragraph 42: Installation of cable ducts

Extent: E+W+S

(1) In the event that the cables comprised within the East Anglia ONE North cable works are installed prior to the cables comprised within the East Anglia TWO cable works, the East Anglia TWO cable works may not subsequently be installed unless the cable ducts forming part of the East Anglia TWO cable works have been installed concurrently with the installation of the cables comprised within the East Anglia ONE North cable works.
(2) For the purposes of this requirement—
(a) “the East Anglia ONE North cable works” mean Work Nos. 6, 8, 9, 11, 12, 13, 16 to 23 and 26 of the East Anglia ONE North Order; and
(b) “the East Anglia TWO cable works” mean Work Nos. 6, 8, 9, 11, 12, 13, 16 to 23 and 26 of this Order.

---
Source: https://www.legislation.gov.uk/uksi/2022/433/schedule/1/paragraph/42 (the official version)
Page: https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-1/paragraph-42
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

