# The East Anglia TWO Offshore Wind Farm Order 2022, Paragraph 43: Restriction on carrying out grid connection works

Extent: E+W+S

No part of the grid connection works may commence under this Order until either—
(a) the offshore works have commenced; or
(b) the undertaker has provided appropriate evidence to the Secretary of State demonstrating its commitment to commence the authorised development described within paragraph 1 of Schedule 1, Part 1 and the Secretary of State has confirmed that the grid connection works may commence.

---
Source: https://www.legislation.gov.uk/uksi/2022/433/schedule/1/paragraph/43 (the official version)